SK Hynix Runs Its Yongin Fab Around the Clock to Open in February

Semiconductor fab under construction at night, surrounded by illuminated cranes

SK hynix is working around the clock on Y1, the first fab at its Yongin semiconductor complex, about 90 minutes from Seoul. Construction is 89% complete, and the company wants to open the first clean room in February 2027, three months ahead of schedule, to produce DRAM and HBM memory for AI demand. According to Nikkei Asia, which visited the site, the building will reach about 150 meters in height and could become the tallest chip plant in the world.

SK hynix’s Y1 fab in Yongin in 30 seconds

  • Y1 is being built nonstop and is 89% complete, with around 20,000 workers on site each day.
  • The first clean room will open in February 2027, three months ahead of the original plan.
  • It will produce DRAM and HBM; investment in Y1 is around 31 trillion won.
  • The complex will have four fabs by 2033, with planned investment of 600 trillion won.
  • Y1 will house a test bed for suppliers, Trinity Fab.

Nikkei Asia’s report, published November 16 after a press visit, describes a roughly 150-meter building — equivalent to a 50-story block — rising among rural hills. South Korean outlets that were on the same visit describe a forest of cranes around the nearly finished structure, with facades starting to close up. According to SK hynix, around 20,000 people work on the site every day, with thousands of vehicles and machines.

The Numbers Behind the Yongin Complex

Yongin is SK hynix’s big industrial bet. The cluster covers about 4.15 million square meters, and the company has committed 600 trillion won to build four fabs. Nikkei puts that at about $450 billion; other outlets give somewhat lower figures, between $390 billion and $410 billion, due to differences in the exchange rate used. It’s part of a plan unveiled in June that totals 1,100 trillion won across Yongin, Cheongju, and a future cluster in the country’s southwest.

Y1 currently accounts for about 31 trillion won, after being expanded in February with five additional clean rooms; it will have up to six, opening in phases. In August, the board approved 35.2 trillion won for Y2, the complex’s second fab, which will begin construction in July 2027. The company has moved up its target for completing all four plants from 2045 to 2033, with planned capacity of between 1.2 and 1.44 million wafers per month.

Why the Rush

The reason is AI memory. SK hynix is one of the leading suppliers of HBM, the stacked memory that pairs with the GPUs in AI accelerators, and demand is outstripping supply. In September, we reported that memory inventories at Samsung and SK hynix had dropped below ten days of supply. Every month gained in opening a clean room is capacity reaching a tight market sooner, which explains the round-the-clock shifts on site.

The other news from the visit was Trinity Fab, a 3,305-square-meter test bed on Y1’s third floor, separated from production by a wall. It will cost 874.6 billion won, funded by SK hynix along with central and local governments, and will let smaller suppliers validate materials and equipment under conditions close to a real production line. It will have just over 50 tools using ArF lithography, not EUV, though SK hynix will offer access to EUV in nearby clean rooms. It will be completed in May 2027 and run at full capacity in the fourth quarter. The company estimates it will cut time-to-market for those products by at least 30%, an estimate whose methodology it hasn’t detailed.

Frequently Asked Questions

When will SK hynix’s Y1 fab start production?

Its first clean room will open in February 2027, three months ahead of the original schedule.

How much will SK hynix invest in Yongin?

600 trillion won for four fabs through 2033; Y1 alone accounts for about 31 trillion won.

What will it produce?

DRAM, including HBM memory for AI accelerators.

What is Trinity Fab?

A test bed inside Y1 where smaller suppliers will be able to validate materials and equipment under conditions similar to a production line.