About 54% of the electricity consumed by large US hyperscale data centers between May 2024 and April 2025 came from natural gas and coal plants, according to the Harvard-led study published in Nature Sustainability. The study, which analyzes 403 facilities with an estimated central consumption of 82 terawatt-hours (TWh), attributes about 25.7 million tons of CO2 to them over that period, according to Tom’s Hardware and Wccftech.
Hyperscale data center emissions in 20 seconds
- Fossil fuels supply close to 54% of the electricity attributed to 403 hyperscale data centers.
- Natural gas accounts for about 38%, coal 15%, nuclear 21%, and renewables 25%.
- Published emissions are around 25.7 million tons of CO2, versus 37-54 million in the June draft.
We already covered the consumption side of this study, which puts the electricity used by these facilities in a range of 68 to 99 TWh, comparable to a country like Chile’s consumption. This piece looks at the other half of the study: where that electricity comes from and how much CO2 it can be attributed to.

Which plants power each data center
A data center doesn’t buy electricity from one specific plant — it draws power from a grid where many sources mix together. To estimate that origin, the authors, led by Gianluca Guidi of Harvard’s T. H. Chan School of Public Health, assign each facility the generation mix of its grid balancing area — the zone where an operator matches supply and demand. For that, they use eGRID, the US Environmental Protection Agency’s (EPA) power-plant database, in its 2023 edition.
The result, according to the preliminary version posted on arXiv in June, is that 53.9% of the electricity attributed to these centers comes from fossil fuels: 38.2% from natural gas and 15.2% from coal. Nuclear contributes 20.9%, and renewables (hydro, wind, solar, biomass, and geothermal) 25.3%. The explanation lies in geography: many of the large campuses cluster in areas with heavy fossil generation, and Virginia, Oregon, Ohio, and Iowa account for more than half of the detected consumption.
This method has its limits. It’s a statistical, grid-based attribution that doesn’t account for the renewable power-purchase agreements many large operators sign, nor for off-grid self-generation. What’s more, eGRID’s data is from 2023, while the period analyzed runs from May 2024 to April 2025, so the real mix that year may have been somewhat different.
The CO2 figures shift between the draft and the published version
One difference is worth clarifying. Outlets reporting on the version published in Nature Sustainability cite about 25.7 million tons of CO2, two to three times the 2018 estimates, according to Wccftech. The June preliminary version, however, estimated 37 to 54 million tons, with 45 million in the central scenario, and an average intensity of 545 grams of CO2 per kilowatt-hour, 48% above the US grid average.
We haven’t been able to review the final text to see what changed during peer review, so both figures should be treated as separate estimates from the same team. What does match across both versions is the source split, with fossil fuels at around 54%, and the consumption range of 68 to 99 TWh.
A calculation that’s probably an undercount
Guidi considers both the consumption and the carbon footprint conservative, since AI infrastructure expansion has continued past April 2025. Ana Valdivia of the University of Oxford, who wasn’t involved in the study, notes that it also doesn’t count some facilities’ own power generation, such as the gas turbines feeding xAI’s Tennessee facility. For the industry, the practical takeaway is that a data center’s footprint depends as much on what it consumes as on where it’s built and which grid it connects to.
Frequently asked questions
Where does the electricity for US hyperscale data centers come from?
According to the study, close to 54% from fossil fuels (about 38% gas and 15% coal), 21% nuclear, and 25% renewables.
How much CO2 do they emit?
The published version, per media reports, puts it at about 25.7 million tons in a year; the June draft estimated 37 to 54 million.
Does it account for renewable energy purchases?
No. It attributes to each center the generation mix of its grid area, without counting renewable power-purchase agreements or self-generation.
Sources:
- Nature Sustainability: Guidi et al. study
- arXiv: preliminary version of the study
- Tom’s Hardware
- Wccftech
This article is also available in Spanish: “Gas y carbón dan más de la mitad de la luz a los centros de datos de EE. UU.,” on revistacloud.com.